July Construction Update

cd4eecea-baf1-4b6f-a731-e7fdf89b5972.jpg

Progress

  • Earthwork mass excavation- 98%
  • Perimeter footing- 99%
  • Perimeter concrete walls- 99%
  • Second floor trusses and walls- 98%
  • Third floor trusses and walls- 98%
  • Retaining walls- 40%
  • Plumbing rough-ins- 50%
  • HVAC rough-ins- 25%
  • Electrical rough-ins- 15%
  • Side utilities- 85%
Next Two Weeks
  • Subs roughing in zone 1 on floors 1-3 and in zone 2 on the 3rd floor
  • Windows and Tyvek underway
  • Framing to wrap up within the next week
  • MEP rough-ins continuing
  • Siding to start in early August