CONSTRUCTION UPDATE

Progress

  • Earthwork mass excavation- 95%
  • Perimeter footing- 99%
  • Perimeter concrete walls- 99%
  • Waterproofing and foundation installation- 95%
  • First floor framing- 60%
  • Precast and the last wall pour are complete
Next Two Weeks
  • Begin underground plumbing and electrical work in the parking garage
  • Finish framing on the first floor
  • Second floor trusses will be installed
Completion expected to be March 2019